HC Deb 03 February 1966 vol 723 cc275-6W
Lord Balniel

asked the Minister of Transport whether she will give a date for the starting of work on the B.190 Stanborough Road, Welwyn Garden City, 20th Mile Bridge, which has been deferred under the proposals for reducing capital expenditure.

Motorways in Use Miles Actual or Estimated Completion Date Actual or Estimated Cost (including land unless otherwise stated) £m.
M. 1—London-Yorkshire
Aldenham-Crick 73 November, 1959 50.5 (main works only)
Crick-Markfield 26¾ October, 1964 and January, 1965
Markfield-Kegworth 11 December, 1965
M.2—Medway Motor Road 25¼ May, July and September, 1963 16.0
M.4—London-South Wales
Slough By-pass April, 1963 4.9
Maidenhead By-pass 6 June, 1961 3.0
Chiswick-Langley 13 November, 1964 and March, 1965 19.5
M. 5—Bristol-Birmingham
Lydiate Ash-Twyning 26 July, 1962 9.4
Lydiate Ash-Quinton 6 November, 1965 6.6
M.5—Filton By-pass
(Classified Motorway built by Glos. C.C.) 21 May, 1963 .74
M. 6—Birmingham-Preston-Carlisle
Dunstan-Preston 78¼ August, 1962-November, 1963 56.1
Preston By-pass 8 December, 1958 5.2
Preston-Lancaster 13¼ January, 1965 11.0
Lancaster By-pass 11½ April, 1960 4.7
M.50—Ross Spur 21½ November, 1960 6.7
M.62—Stretford-Eccles By-pass
(Classified Motorway built by Lanes. C.C.) 6 October, 1960 5.6
A.1(M) Doncaster By-pass 15½ July, 1961 6.5
Stevenage By-pass 7 July, 1962 2.2
Darlington-Barton By-pass 13 May, 1965 6.5
A.20(M)—Maidstone By-pass June and December, 1960 2.6
375½

Mr. Swingler

Work should start next June.