HC Deb 20 December 1966 vol 738 cc301-2W
Mr. Emrys Hughes

asked the Minister of Public Building and Works what is the estimated cost of the work at the Polaris base at Faslane up to 31st December, 1966 not included in the cost borne by the Admiralty; and if he will state the cost of his work at the Polaris school and the other items of expenditure still to be undertaken.

Mr. Boyden

£12 million (including associated work at Coulport, Helens-burgh and elsewhere). I would refer my hon. Friend to my right hon. Friend's answer of 29th April, 1966, about the Polaris School, where only minor items remain to be done.—[Vol. 727, c.64.]