§ Lord Balnielasked the Minister of Transport why the Southern Link Road, Hatfield New Town, which was originally scheduled to start in October, 1965, has been postponed for more than six months.
§ Mr. SwinglerThere was no delay. The contractor started preparatory work in April and main works started two days after the expiry of the deferment period.