HC Deb 11 March 1965 vol 708 c126W
Mr. Gower

asked the Secretary of State for Wales what improvements will be carried out during the next 12 months along the route of the North-to-South Wales road; and if he will state the approximate cost of these improvements.

Mr. Finch

The following ten major improvement schemes are planned, at an estimated total cost of£210,000:

The schemes to be put in hand in the next 12 months are:

£
Merionethshire:
A.487. Widening and improvement from Capel Jerusalem to Bronaber 55,000
A.487. Improvement at Ganllwyd village 12,909
A.487. Widening and improvement at Bryn Cemlyn, Ganllwyd 5,200
Montgomeryshire:
A.492. Widening of Penrhuddlan Bridge 19,000
Radnor:
A.44. Improvement at Neuadd Ddu 42,100
A.479. Improvement at Upper Dolhelfar 17,726
A.479. Improvement at Tanyard Pitch 29,200
£181,135

In addition, the following schemes may be put in hand during the next 12 months if the necessary land is acquired in time:

£
Merionethshire:
A.458. Improvement at Pont Cerist near Dinas Mawddwy 23,750
Montgomeryshire:
A.489. Improvement at junction with B.4568 at Pont Dolgoch 1,838
Radnor:
A.479. Improvement at Melindwr, Newbridge-on-Wye 3,500
£29,088

A number of minor improvements to short lengths of the trunk road will also be carried out.