§ 56. Mr. Emrys Hughesasked the Secretary of State for Defence what expenditure has been incurred up to the end of January on the proposed base for Polaris submarines on the Gareloch; what is now the estimated cost of the base; when it is to be completed; and how many men are now employed on it.
156W
§ Mr. J. P. W. Mallalieu£2.5 million and at current prices and on plans inherited from our predecessors somewhere under £45 million. The base will complete in stages in time to support the first Polaris submarine in July, 1968. About 800 men are now employed on the site.