HC Deb 11 November 1964 vol 701 cc73-4W
59. Mr. Sorensen

asked the Minister of Transport when it is anticipated that road reconstruction in the vicinity of the Green Man, Leytonstone, will be completed; and if he is satisfied that temporary provision for traffic is adequate in view of the heavy traffic load and frequent congestion at that point.

Mr. T. Fraser

Reconstruction of the junction at the Green Man, Leytonstone should be completed in October, 1965. Arrangements for traffic during the different stages of reconstruction have been planned carefully with the police, who tell me that they are working well so far.