HC Deb 29 June 1964 vol 697 cc148-9W
58. Mr. Swingler

asked the Minister of Health on what date the plans and estimates for the new maternity wing in North Staffordshire, originally due to be begun in early 1964, were first completed; at what stage it was decided that a more comprehensive geological survey of the site was necessary; what changes in plans and estimates have resulted from this survey; what is now the ealiest date on which work can begin; and if he will ensure maximum speed in construction in view of the urgent need.

Mr. Braine

Working drawings were first completed last December and bills of quantities last March; the Board commissioned a geological survey in March, 1961; the working drawings had to be adapted before completion to give stronger foundations and structure and to incorporate engineering precautions against subsidence which increased the original estimate; work should start in the autumn, and my right hon. Friend will see that it proceeds without delay.