HC Deb 23 May 1963 vol 678 c62W
49. Sir K. Thompson

asked the Minister of Education when he expects the reorganisation of the remaining all-age schools in Liverpool to be completed.

Mr. Chataway

The Liverpool authority's 1964–65 major school building programme, which was announced in February this year, includes all the new secondary schools required to complete the reorganisation of the authority's remaining all-gage schools. Nine new schools are needed, costing nearly £2 million. If all these projects are started in the programme year it should be possible to complete reorganisation within about two years thereafter.