§ Mr. Farrasked the Minister of Transport (1) by what date he now expects 204W the M.1 to be in use between Crick and Whetstone;
(2) by what date he now expects the section of M.1 between Whetstone and Kirby Muxloe to be completed.
§ Mr. MarplesThe Crick to Whetstone section is expected to be completed and its southern portion up to the Lutter worth junction with A.4114 brought into use in Autumn 1964. The remainder will come into use on completion of the Whetstone to Kirby Muxloe section which is expected to be in spring 1965.
§ Mr. Kenyonasked the Minister of Transport if he will state the cost per year for maintenance of the M.I motorway for each year since the motorway was opened.
§ Mr. MarplesThe costs of normal maintenance and of special repairs to the carriageways, which include strengthening to current standards, are:
— Normal Maintenance Special Repairs £ £ 1960–61 … 150,000 — 1961–62 … 130,000 59,000 1962–63 … 130,000 203,000 1963–64 … 130,000 90,000 TOTALS … 540,000 352,000 In addition a number of improvements are being made, such as widening and strengthening the hard shoulders and extending the drainage, to bring the motorway up to present day standard.