HC Deb 17 December 1963 vol 686 c200W
Mr. Hamilton

asked the Minister of Public Building and Works what was the final cost of the rebuilding of 10 Downing Street, including the cost of furnishings; and how the cost compares with the original estimate.

Mr. Rippon

Final accounts will not be settled for some time, but the present estimate for Nos. 10, 11 and 12 Downing Street is £1 million for building work and £33,000 for furnishings. The original estimate was £500,000 for building work and £29,000 for furnishings.