HC Deb 03 May 1960 vol 622 c53W
Sir T. Moore

asked the Secretary of State for Scotland if he will issue a list of schemes in the road programme cost-

Scheme Starting Date Estimated completion Date Estimated total Cost
Trunk Roads £
1. A.77 Improvement from Malletsheugh to Woodvale Avenue, Renfrewshire. November, 1959 Summer 1962 551,000
2. A.78 Kilwinning By-pass, Ayrshire November, 1959 Spring 1962 448,000
3. A.78 Ayr-Prestwick By-pass (Stage 1), Ayrshire. November, 1959 Summer 1961 706,000
4. A.76 Howford Bridge Diversion, Ayrshire August, 1959 Summer 1961 414,000
5. A.9 Improvement from Blueton to West of Blackford, Perthshire. November, 1959 Summer 1961 136,000
6. A.1 Scrogend and Houndwood Diversions, Berwickshire. April, 1959 Summer 1960 109,000
7. A.74 Abington and Crawford Diversions, Lanarkshire. March, 1960 Spring 1962 723,000
8. A.74 Improvement between Lockerbie and Ecclefechan, Dumfriesshire. November, 1959 Winter 1961 592,000
9. A.74 Reconstruction of Birkwood Bridge May, 1959 Winter 1959 174,000
10. A.83 Improvement from Loin Bridge to Black Spout, Argyll. January, 1960 Autumn 1961 166,000
Classified Roads
11. A.83 Reconstruction between Tarbert and Ronachan, Argyll. March, 1960 Summer 1962 178,000
12.. C1. III Widening and reconstruction of Broomhouse Road, Edinburgh. April, 1955 Summer 1961 198,000
13. Clyde Tunnel, Glasgow. Construction of Tunnel No. 2. December, 1959 Summer 1963 3,881,000
14. A.86 Reconstruction from Roy Bridge to Roughburn, Inverness-shire. June, 1959 Summer 1961 188,000
15. A.9 Replacement of Suspension Bridge, Inverness. August, 1959 Summer 1961 302,000
16. Potential Class I. Widening of Canal Street, Paisley. April, 1959 Summer 1960 134,000
17. A.85 Replacement of Victoria Bridge, Perth May, 1959 Summer 1960 160,000
18. A.832 Reconstruction of Gruinard Hill, Ross and Cromarty. June, 1959 Spring 1961 106,000
Note
Trunk road scheme No. 9 is part of the larger scheme of the improvement of A.74 between Lesmahagow and Canderdyke, Lanarkshire.