§ 43. Mr. John Hallasked the Minister of Transport what are the causes of the delay in completing the Hanger Lane under-pass on Western Avenue.
85. Mr. Pages asked the Minister of Transport what was the date of starting work on the Western Avenue under-pass at Hanger Lane; and what were the estimated cost and date of completion then and at the present time.
§ Mr. MarplesWork started in June, 1958. The contract price was £761,000 and the completion date March, 1960. Subsequently the contract period was extended for three months to June, 1960. The under-pass should be completed in October, but the pedestrian subways not before the end of the year. I am hoping to arrange for one of the tunnels to be brought into temporary use within the next few weeks for one way traffic, whilst the other tunnel is being completed. I understand that the main cause of delay142W has been the contractors' difficulty in obtaining suitable labour. The cost of the scheme is now estimated at £830,000.