Sir A. Bossom

asked the Minister of Works to give in the OFFICIAL REPORT for the three largest building contracts undertaken in the last five years, either for his own Department or on behalf of other Departments, the date when the contract to build was signed, the date stated in the contract or agreed before the work started when the undertaking should be completed, the date when the building was actually completed and accepted by the Department concerned, and the date when

Date contract was signed Contract date for completion Actual date of completion Final payment to contractor
(a) 13th September, 1951 18th February, 1953 16th July, 1953 9th October, 1955
(b) 23rd November, 1951 28th May, 1953 7th March, 1955 22nd October, 1956
(c) 12th May, 1952 13th February, 1954 20th January, 1954 21st February, 1955