HC Deb 29 January 1957 vol 563 cc140-1W
43. Mr. Steele

asked the Secretary of State for Scotland what is causing the delay in the completion of the new school at Mill-of-Haldane, Balloch; and when he expects the school to be ready.

Mr. Maclay

Some delay has been caused by late delivery of materials and by a shortage of plasterers. The education authority expects the infant block to be ready for occupation in about a month's time and it hopes that the rest of the school will be completed in the autumn.

44. Mr. Steele

asked the Secretary of State for Scotland when he expects work to start on the new Roman Catholic school at Balloch.

Mr. Maclay

Work on this school is expected to start towards the end of this year.