HC Deb 29 March 1956 vol 550 c239W
Mr. Viant

asked the Minister of Transport and Civil Aviation the average time taken for the preparation of details and contract documents for a major road scheme; and how long is the average delay between authorisation and commencement of work.

Mr. Watkinson

While the period naturally varies according to the size and complexity of the scheme and the availability of engineering staff, the preparation of details and contract documents for a major road scheme takes, on average, between twelve and eighteen months. For a representative selection of large trunk road schemes started in the past two years the average time between authorisation and commencement of work has been eleven months.