HC Deb 18 December 1956 vol 562 cc134-5W
78. Sir W. Anstruther-Gray

asked the Secretary of State for Scotland the estimated dates of completion of the road schemes for Scotland which have already been announced.

Mr. J. Stuart

The following statement shows the dates at which it is at present estimated that the schemes costing over £100,000 listed in my reply to the hon.

Road Scheme Estimated date of Completion
(a) Trunk Roads
A.8 Reconstruction of railway bridge, Langbank Early 1959
A.9 Reconstruction of Bridge of Allan Mid-1958
A.9 Linlithgow Bridge Early 1959
A.74 Johnstone Bridge-Beattock Mid-1959
A.77 Wigtown County Boundary northwards Late 1958
A.80 Luggie Water to west of Cumbernauld Early 1959
A.80 Cardowan Road, Stepps, to Mollinsburn Late 1959
A.82 Dumbuck to Barloan Crescent Late 1957
A.92 Widening of Bridge of Don Late 1958
A.96 Sheriffmill Bridge Late 1958
(b) Classified roads
A.8/A.814 Whiteinch Tunnel No. 1 1962 or 1963
A.72 Kirkfieldbank Bridge Mid-1958
A.81 Gartmore Bridges End 1958
A.815 St. Catherine's-Strachur Mid-1957
A.838 Rhiconich-Gualin End 1957
A.851 Broadford-Armadale End 1956
A.865 North Ford Causeway End 1958
A.92 Widening of Bridge of Don Late 1958
A.965 Leven Bridge Mid-1957
Class III Ford-Kilchrennan Early 1959
Construction of roads in East Kilbride Continuing programme of works.