HC Deb 06 December 1956 vol 561 cc166-7W
Mr. Mason

asked the Lord Privy Seal to what extent the Calder Hall Atomic Power Station has been continually producing electricity since put on to the grid; whether it has consistently maintained its output; and if he will make a statement.

Mr. R. A. Butler

I am informed by the Atomic Energy Authority that, except for periods from 5th to 12th November and from 14th to 22nd November, when the reactor was shut down for examination, Calder Hall has produced electricity continuously since 17th October. The reactor is being run to capacity, apart from slight variations to allow checks of equipment, which will continue for some time.

Forward to