HC Deb 26 February 1953 vol 511 c240W
Mr. Russell

asked the Minister of Transport how long the work of widening A5 at Elstree will take; how much time has been lost owing to bad weather; and when north bound traffic will be restored to its normal route.

Mr. Lennox-Boyd

This work has been delayed for about two weeks by bad weather. I expect that north bound traffic will be restored to its normal route in about three weeks' time and that the whole work will be completed about the end of March.