HC Deb 19 May 1952 vol 501 c14W
85. sir A. Gridley

asked the Minister of Fuel and Power the total generating plant capacity available in the aggregate in all the power stations of the British Electricity Authority on 31st December, 1951; and what aggregate additions thereto for operation on 31st December, 1952, have been authorised by him as part of the Authority's capital investment programme.

Mr. Geoffrey Lloyd

The output capacity of the power stations of the British Electricity Authority on the 31st December, 1951, was 14,147,000 kilowatts. They have been authorised under the capital investment programme to bring into operation 1,250,000 kilowatts of new plant in 1952.