HC Deb 16 December 1947 vol 445 c313W
75. Mr. W. Ross

asked the President of the Board of Trade the cost to date of the development of the Kilwinning Industrial Estate; how many factory units have been completed; and how they are presently being used.

Mr. Belcher

The amount spent to date on actual development work on the Kilwinning Estate is just over £60,000, to which should be added £3,400 for cost of acquiring the site and £22,500 for cost of actual building to date. A factory block of 30,000 square feet is nearing completion but is not yet ready for occupation.