HC Deb 19 January 1943 vol 386 cc60-1W
Sir R. Tasker

asked the Parliamentary Secretary to the Ministry of Works and Planning why he has authorised a charge of 1s. 6d. per ton on all cement; from what date does such increase in price operate; and whether additional charges have been authorised upon any other building materials?

Mr. Hicks

The addition of 1s. 6d. per ton, which applies only to Portland and-rapid hardening cement, took effect as from 27th August last and was authorised on account of increases in production costs. My Noble Friend has not, since the date mentioned, authorised increased selling prices of any other materials controlled by the Ministry.

Forward to