HC Deb 01 March 1915 vol 70 c583W
Mr. KING

asked the hon. Member for Saffron Walden, as representing the First Commissioner of Works, what the total cost is expected to be of the work in progress on Westminster Hall roof; and whether the amounts estimated for scaffolding, ironwork, timber work, labour, and all other expenses can be separately given?

Mr. BECK

The total cost is expected to be slightly over £60,000. The estimates for the various parts of the work are as follows:—

£
Steel scaffold, erection, demolition, etc. 3,750
Steel reinforcement 10,530
Steel reinforcement labour 12,285
Timber and treatment with preservative and slating 13,950
Timber and treatment with preservative and slating labour 14,500
Clerk of Works' salary (6 years) and contingencies 5,000
Total £60,015