HC Deb 21 January 2004 vol 416 c1358W
Dr. Richard Taylor

To ask the Secretary of State for Health what the reasons are for the delay in opening the Kidderminster diagnostic and treatment centre; and whether the contractors are subject to penalty payments. [148698]

Dr. Ladyman

The Kidderminster Treatment Centre has changed significantly from the project as it was originally envisaged. There has been extra investment in services and facilities, including an additional operating theatre.

The contract was agreed on a fixed price basis, which has both protected the Worcestershire Acute Hospitals national health service trust from unexpected financial pressures, and removed the need to impose penalty payments on the contractors.