§ Mr. SayeedTo ask the Secretary of State for Trade and Industry if she will list IT contracts in her Department above £50 million in each of the last 10 years; what the inception date for each system was; when it became fully functional; when it became fully debugged; and what the cost of over-runs has been. [98999]
§ Ms HewittThe core Department has let one IT contract with a lifetime value of more than 50 million in the last 10 years. This is the ELGAR PFI contract for the provision of IT desktop, application support and development, and business re-engineering services.
The contract was awarded on 27 November 1998 and the initial service became operational on 31 March 1999, as planned. System Acceptance testing of the new desk top service was completed on 30 November 1999, and the system became fully functional on 31 March 2000. Following user acceptance testing, the system was accepted by the Department and the system was fully debugged by 15 July 2000.
There were no additional costs to the Department for over-runs on this migration.