HC Deb 30 January 2002 vol 379 c382W
Miss McIntosh

To ask the Secretary of State for Trade and Industry what action she has taken to curb the number of overhead transmission lines that have been planned for the future. [30143]

Mr. Wilson

The National Grid company has a duty to develop and maintain an efficient, co-ordinated and economical system of electricity transmission. It is a matter for that company what proposals it brings forward. These applications are then considered by the Department in the section 37 procedure and decisions reached on them.

Miss McIntosh

To ask the Secretary of State for Trade and Industry what measures she has taken to ensure that National Grid abides by the relevant planning conditions when erecting pylons for the Lackenby to Shipton overhead transmission lines, with particular reference to access to land in dry conditions. [30142]

Mr. Wilson

It is a matter for the relevant local planning authorities to enforce the planning conditions applied to the North Yorkshire power line. However, where there is doubt over the interpretation of a condition the Department has been willing to provide clarification.

Forward to