HC Deb 17 January 2002 vol 378 cc428-9W
Mr. Menzies Campbell

To ask the Secretary of State for International Development what estimate her Department has made of the cost to its budget since 1 May 1997 of fraud; and if she will make a statement. [27294]

Clare Short

The estimated cost to DFID' s budget of fraud in the period 1 April 1997 to 31 March 2001 is some £250,000, of which £175,000 can be attributed to contractor fraud. Of the remaining sum, £22,000 relates to the theft of assets which, in line with Treasury guidance, has been classified as involving departmental staff either directly or through collusion. Details of suspected or proven fraud are provided to the Treasury on an annual basis. The annual report that the Treasury prepares on fraud is deposited in the Libraries of both Houses.