§ Jane GriffithsTo ask the Secretary of State for Transport, Local Government and the Regions when each of the modal studies proposed in the 10-year transport plan will be(a) completed and (b) published. [50041]
§ Mr. JamiesonThe multi-modal studies that have been completed and a final report published are as follows.
Multi-modal study and location Reported Access to Hastings December 2000 Cambridge to Huntingdon (A14) August 2001 South East Manchester (Stockport, Manchester Airport Link West, Poynton) September 2001 West Midlands area (M5/M6 and M42 between M40 and M6) October 2001 The following table shows expected completion/final report dates of the multi-modal studies that are currently in progress:
§ Mr. Byers[holding answer 23 April 2002]: The summary papers were produced at the end of January and early February. The titles of those attending are Director, Divisional Manager, Branch Head, Senior Executive Officer, Higher Executive Officer, Network Strategy Manager, MMS Project Manager, Assistant Project Manager, MMS Technical Director.