To ask the Secretary of State for Transport, Local Government and the Regions what estimate he has made of the total savings of the Private Finance Initiative contract for the(a) Ml/A1 Link Road, (b) A 1 (M), (c) A30/35, (d)M40, (e) A417/419, (f) A19, (g) A50, (h) A69 and (i) second Severn Crossing by comparison with a non-Private Finance Initiative alternative. [49271]

Mr. Jamieson

The following figures show the savings estimated at the time of contract award.

£ million
Project Public sector comparator Winning DBFO bid Estimated saving
M1-A1 344 232 112
A1(M) 204 154 50
A419/A417 123 112 11
A69 57 62 (5)
M40 276 182 94
A19 177 136 41
A50 77 67 10
A30/A35 149 148 1
Total 1,407 1,093 314

Note:

Figures are net present values calculated at an 8 per cent. real discount rate. This was the rate used for assessing road projects at the time of contract award.

I understand that the publicly and privately financed options for the second Severn Crossing were evenly matched.