HC Deb 17 July 2001 vol 372 cc162-3W
Mr. Dobson

To ask the Secretary of State for Northern Ireland if he will list the Information Technology contracts in excess of £500,000 let by his Department or its predecessor since April 1991, giving in each case the original estimated cost and original estimated completion date, the actual cost and actual completion date and the

Estimated cost Estimated completion Actual cost (£) Actual completion Contractor Consultant
Oasis
£5,000,000 December 1996 5,732,000 November 1997 Bull
DPPNet
£750,000 February 1999 748,000 March 1999 Bull
Bloody Sunday InquiryContract A
£1,800,000 June 1998 2,500,000 (includes changes and additional input) June 1998 Bull
Bloody Sunday InquiryContract B Hearings Installation
£2,000,000 March 2000 2,000,000 (fixed price setup contract) March 2000 ICL Deloitte and Touche
Bloody Sunday InquiryContract C Hearings Running Costs
£5,000,000 Not known Ongoing based on fixed cost of 225k per month Not known ICL Deloitte and Touche
Oasis Refresh
£1,900,000 October 1999 2,255,000 December 1999 Compaq
Compass
£1,200,000 November 2002 On budget On target Picaso