HC Deb 26 February 2001 vol 363 c405W
Dr. Tonge

To ask the Secretary of State for Trade and Industry how many credits haye been supplied by

10 April 2002
Financial year No. Case Market Value £ million Guarantee date Project completion date
1990–91 1 Hydro Electric Powei project (Ewaso Ngiro) Kenya 21 21 December 1990 30 September 2000
1991–92 3 Design and Construct 600 MW Hydro-electric power Plant "Pergau" Malaysia 328 31 July 1991 30 April 2001
As above Malaysia 119 15 April 1991 30 April 2001
As above Malaysia 153 15 March 1992 30 April 2001
1993–94 1 Muela Hydropower Project (phase 1A) Lesotho 1 17 February 1994 31 March 2000
1994–95 2 Hydro Electric Plant and Sub Stations Thailand 17 13 September 1994 31 March 2002
Muela Hydropower project (phase 1 A) Lesotho 7 14 April 1994 31 March 2000
1995–96 4 Design and Equipment for Guangdong Ling Ao Nuclear Power Station China 576 20 December 1995 30 August 2003
Goods and Services lor Qinshan Phase II Nuclear Power Station China 37 11 January 1996 30 April 2001
Muela Hydropower Lesotho 4 15 December 1995 31 March 2000
Muela Hydropower Lesotho 1 15 December 1995 31 March 2000
1996–97 2 Muela Hydropower Project Contract LHDA 129A Lesotho 3 24 January 1997 30 April 1999
Qinshan Phase 11 Nuclear Power Plant China 17 15 May 1996 15 February 2002
1999–2000 1 Weir Westgarth/Flash Thermal Plant at Ghubrah Oman 10 2 November 1999 Ghubrah