HC Deb 03 December 1997 vol 302 c221W
Mr. Allan

To ask the Secretary of State for the Environment, Transport and the Regions what were(a) the projected and (b) the outturn costs to public funds of the South Yorkshire Supertram. [18220]

Ms Glenda Jackson

The South Yorkshire Supertram scheme was forecast to cost £240.610 million in outturn prices. The final outturn expenditure reported by South Yorkshire Passenger Transport Executive in March 1997 was £240.609 million.