HC Deb 14 November 1996 vol 285 c302W
Mr. Andrew Smith

To ask the Secretary of State for Transport what is the planned timetable for completion of refurbishment work on the Shoreditch to New Cross/New Cross Gate underground line; what was the original timetable; when the line will reopen; and if he will make a statement. [3869]

Mr. Bowis

I understand that London Underground's refurbishment and tunnel strengthening works on the East London line are well under way and that London Underground is aiming to complete the works and re-commission the line in time to re-open it in late summer 1997. The works were originally programmed to take place between March and October 1995. They are now proceeding on schedule.