HC Deb 19 April 1995 vol 258 c153W
Miss Lestor

To ask the Secretary of State for Foreign and Commonwealth Affairs, pursuant to his written answer of 27 March,Official Report, column 444, for what reason expenditure on the Pergau dam project was not listed in table 1 on page 34 of the supply estimates, class II for 1991–92, HC 236–II; and under which subhead of which vote parliamentary authority was sought for expenditure in 1991–92. [18706]

Mr. Baldry

Table I of the 1991–92 estimate for class II, vote 5 lists projects on which expenditure had been incurred up to March 1991. This project became effective only in July 1991. Expenditure in 1991–92 was incurred under class II, vote 5, subhead A2.