HC Deb 14 June 1994 vol 244 cc538-45W
Mr. Llwyd

To ask the Secretary of State for Wales if he will publish for each county and district council what allocation of funding has been made under the strategic development scheme and its predecessor schemes, including the urban programmes, rural initiative, projects of national and regional importance and special projects, for the last three years and for 1994–95.

Mr. Redwood

[pursuant to his reply, 19 April 1994,c. 460–66]: I regret that the table provided with my reply to the hon. Member was incorrect. A revised table providing the corrected information is given as follows:

Local authority and programme 1991–92 including UP holiday project 1992–93 11993–94 41994–95
Rhuddlan BC
RI 147,000 27,000
UP 544,500 1,125,000 1,137,554
PRNI/SP 840,000 825,000 1,200,000
SDS 820,867
Wrexham Maelor BC
RI
UP 1,449,203 549,559 246,401
PRNI/SP 1,350,000 200,000 2,085,000
SDS 1,487,336
Dyfed CC
RI 553,000 2,312,700 838,500
UP 472,538 308,684 351,184
PRNI/SP
SDS 21,289,653
Carmarthen DC
RI 557,650 126,500 120,000
UP 136,438 17,865 17,865
PRNI/SP
SDS 3183,933
Ceredigion DC
RI 140,000 240,000 302,000
UP 137,127 107,163 76,781
PRNI/SP 500,000
SDS 3975,194
Dinefwr BC
RI 78,000 125,000 236,000
UP 687,731 1,080,375 427,830
PRNI/SP 900,000 600,000
SDS 1,443,915
Llanelli BC
RI
UP 442,327 1,095,627 764,057
PRNI/SP 1,000,000 1,200,000 1,500,000
SDS 2,224,300
Preseli Pembs DC
RI 33,450 347,104 1,021,460
UP 283,080 112,439 140,000
PRNI/SP 650,000 700,000
SDS 927,015
South Pembs DC
RI 60,000 146,000 678,340
UP 219,247 193,000 221,792
PRNI/SP 1,000,000
SDS 2,481,272
Gwent CC
RI
UP 5,499,696 2,234,987 1,355,759
PRNI/SP 1,054,000 500,000 500,000
SDS 2,389,256
Blaenau Gwent, BC
RI 9,800
UP 5,885,725 1,680,885 915,728
PRNI/SP 1,055,000 700,000 655,000
SDS 1,752,723
Islwyn BC
RI
UP 1,070,884 840,476 722,920
PRNI/SP
SDS 1,266,908
Monmouth DC
RI 236,000 211,000 56,911
UP 31,683 29,724 203,306
PRNI/SP

Local authority and programme 1991–92 including UP holiday project 1992–93 11993–94 41994–95
SDS 57,873
Newport BC
RI
UP 703,392 815,426 1,039,886
PRN1/SP
SDS 1,153,335
Torfaen BC
RI
UP 821,739 464,436 345,344
PRNI/SP
SDS 640,075
Gwynedd CC
RI 410,000 208,000 641,000
UP 674,774 1,495,728 1,460,011
PRNI/SP 248,000 806,000
SDS 2,310,629
Aberconwy BC
RI 617,983 440,000
UP 260,900 190,900 170,450
PRNI/SP 759,000 2,185,000
SDS 1,150,000
Arfon BC
RI 300,000 94,500 590,000
UP 512,403 656,932 381,854
PRNI/SP
SDS 1,126,060
Dwyfor DC
RI 250,000 156,400 501,300
UP 150,000 121,475
PRNI/SP 1,400,000 1,900,000
SDS 787,464
Meirionnydd DC
RI 100,000 526,100
UP 402,039 221,029 157,595
PRNI/SP
SDS 667,826
Ynys Mon BC
RI 52,000 135,000 390,000
UP 538,406 318,282 127,071
PRNI/SP
SDS 1,140,368
Mid Glamorgan CC
RI
UP 2,183,187 2,374,309 2,195,545
PRNI/SP 7,430,000 3,550,000
SDS 2,595,176
Cynon Valley BC
RI
UP 2,284,621 2,322,765 1,775,532
PRNI/SP
SDS 1,946,880
Merthyr Tydfil BC
RI
UP 1,071,184 1,487,581 987,046
PRNI/SP
SDS 902,769
Ogwr BC
RI
UP 1,195,108 1,355,902 1,165,412
PRNI/SP 1,102,276
SDS
Rhondda BC
RI
UP 1,836,311 1,899,285 2,804,766

Local authority and programme 1991–92 including UP holiday project 1992–93 11993–94 41994–95
PRNI/SP 900,000
SDS 4,460,290
Rhymney Valley DC
RI
UP 655,358 1,161,266 744,720
PRNI/SP
SDS 800,000
Taff-Ely BC
RI
UP 675,850 1,084,591 533,282
PRNI/SP 350,000
SDS 430,789
Powys CC
RI 277,122 500,000 317,000
UP 491,158 114,640 90,566
PRNI/SP
SDS 774,738
Brecknock BC
RI 360,000 110,000
UP 27,000 250,000
PRNI/SP 1,316,000 2,330,000
SDS
Montgomeryshire DC
RI 580,000 196,826 262,000
UP
PRNI/SP
SDS 125,790
Radnor DC
RI 420,000 31,000
UP 14,686 15,836 15,836
PRNI/SP 805,000 250,000
SDS 182,918
South Glamorgan CC
RI
UP 1,166,343 1,624,470 1,339,602
PRNI/SP 400,000
SDS 1,227,698
Cardiff CC
RI
UP 1,229,534 1,076,683 1,310,492
PRNI/SP
SDS 988,961
Vale of Glamorgan BC
RI
UP 298,710 577,677 760,882
PRNI/SP
SDS 1,189,632
West Glamorgan CC
RI
UP 1,123,304 1,344,746 1,632,821
PRNI/SP 300,000 1,879,000
SDS 2,281,353
Port Talbot BC
RI
UP 630,700 183,047 323,809
PRNI
SDS 252,797
Lliw Valley BC
RI 8,344
UP 309,300 432,078 338,504
PRNI/SP
SDS 281,758
Neath BC
RI
UP 823,520 679,811 314,785

Local authority and programme 1991–92 including UP holiday project 1992–93 11993–94 41994–95
PRNI/SP
SDS 352,311
Swansea CC
RI
UP 574,727 544,277 964,804
PRNI/SP 1,239,000 165,000
SDS 2,625,245
1 Includes additional in-year allocations.
2 Includes £0.5 million available to any local authority within the West Wales task force area.
3 Does not include £1.9 million set aside for projects supported in principle for Carmarthen DC and Ceredigion DC.
4 Includes slippage on schemes carried forward from 1993–94 and £10,000 revenue allocation for each of the five successful Community revival strategies, but excludes the capital allocations which will not be confirmed until receipt of the business plans in June 1994 or the money set aside for the development of the industrial village concept.

Back to
Forward to