§ Mr. DenhamTo ask the Secretary of State for the Environment what is the total cost to date of the Ordnance Survey market-testing programme.
§ Mr. AtkinsThe total cost to date of the market-testing programme which commenced in April 1992 is £342,500 including full staff costs and consultants' fees. The management and staff costs incurred before April 1992 were not specifically attributed to market-testing.
§ Mr. DenhamTo ask the Secretary of State for the Environment what is the expected total cost of the Ordnance Survey market-testing programme.
§ Mr. AtkinsThe total cost of the existing market-testing programme which commenced in April 1992 and is310W planned to end in March 1994 is expected to be £413,250; this comprises both management costs and consultancy fees.
§ Mr. DenhamTo ask the Secretary of State for the Environment what management consultants have been used to advise on market-testing in connection with Ordnance Survey; for what purposes; and at what cost.
§ Mr. AtkinsThe following management consultants have been engaged in assisting Ordnance Sui vey with its market-testing programme at a total cost of £113,750:
- Coopers and Lybrand
- CSL Group Ltd.
- Grosvenor Consulting Ltd.
- Tricon FoodService Consultants
Consultants provided scoping advice, advised on the preparation of service specifications and assisted in the assessment of potential bidders, preparing in-house bids and analysing tenders.
§ Mr. DenhamTo ask the Secretary of State for the Environment what was the total management and staff costs for the project board teams associated with the Ordnance Survey market-testing programme.
§ Mr. AtkinsThe total management and staff costs to date for market-testing project teams in Ordnance Survey are £249,000.
§ Mr. DenhamTo ask the Secretary of State for the Environment what savings have been made as a result of the Ordnance Survey market-testing programme.
§ Mr. AtkinsProjected annual savings resulting from the market-testing programme which commenced in April 1992 are £1,554,580. Further benefits include the acceleration of the development and production of base data for new products.
§ Mr. DenhamTo ask the Secretary of State for the Environment what was the total cost in 1992–93 of the Ordnance Survey market-testing programme.
§ Mr. AtkinsThe total cost in the financial year 1992–93 was £230,000.