§ Mr. LidingtonTo ask the Secretary of State for Transport if he will make a statement on(a) the present stage of preparation and estimated timetable for completion and (b) the latest estimate of cost of the (i) Braintree-Al2, (ii) Stansted-Braintree, (iii) A1-Stansted, (iv) A5-A1, (v) Leighton Linslade bypass, (vi) Wing
226W
Bids for transport supplementary grant-1994–95 Structural maintenance Authority Major schemes £k Principal road carriageways £k Bridges £k Total TSG bid £k City of London 0 0 1,106 1,106 Barking and Dagenham 5,017 587 250 5,854 Barnet 0 200 498 698 Bexley 5,614 1,250 970 7,834 Brent 190 1,013 1,249 2,452 Bromley 497 640 344 1,481 Camden 0 1,773 3,085 4,858 Croydon 6,440 2,263 181 8,884 Ealing 1,525 571 372 2,468 Enfield 3,889 404 2,492 6,785 Greenwich 1,615 708 708 3,031 Hackney 1,418 1,013 1,700 4,131 Hammersmith and Fulham 0 1,045 2,255 3,300 Haringey 990 1,544 700 3,234 Harrow 7,551 416 953 8,920 Havering 0 72 563 635 Hillingdon 2,630 364 2,210 5,204 Hounslow 3,159 540 937 4,636 Islington 0 1,220 715 1,935 Kensington and Chelsea 538 166 36 740 Kingston upon Thames 3,992 700 567 5,259 Lambeth 0 630 936 1,566 Lewisham 8,552 300 260 9,112 Merton 685 222 110 1,017 Newham 3,808 70 6,526 10,404 Redbridge 0 705 1,310 2,015 Richmond upon Thames 0 260 515 775 Southwark 2,413 500 430 3,343 Sutton 800 210 468 1,478 bypass, (vii) west of Aylesbury-Wing bypass and (viii) M40-west of Aylesbury stages of the proposed east-west route.
§ Mr. KeyMost of the schemes which comprise the east-west route are at early stages in their development. It is difficult to be certain of the programme and cost. The latest planning data are as follows and are subject to the availability of funding and completion of statutory procedures.
- (i) Braintree-Al2: public consultation early 1994. Cost £39 million—all costs area at Q1/92 prices.
- (ii) Stansted-Braintree: awaiting decision following public inquiry. Cost £68.5 million.
- (iii and iv) A5-Stansted—includes A5-A1 and Al-Stansted: public consultation autumn 1994. Completion year 2001. Cost £462.1 million.
- (v) Leighton Linslade bypass: opened to traffic November 1991. Cost £22 million.
- (vi) Wing bypass: decision following planning inquiry expected shortly. Cost £15 million.
- (vi) West of Aylesbury to Wing bypass: public consultation period just completed. Decision about preferred route expected in 1994. Cost £97 million.
- (vii) M40-west of Aylesbury: no decisions have been made whether or when schemes will enter the trunk roads programme.