HC Deb 13 May 1992 vol 207 c107W
Mr. William Powell

To ask the Secretary of State for Transport what improvements to the A13 between the North Circular road and Butcher row are currently being undertaken; at what cost; and when they will begin and be completed.

Mr. Norris

The present estimated cost of works (including any advance works) and construction dates are as follows:

Scheme Estimated works cost(£ million) Planned start Planned finish
Butcher row junction 1 1993 1994
West India Dock road junction
Interim 4 (Completed April 1992)
Final 1 1993 1993
Cotton street-Blackwall tunnel junction(A 102) 7 1993 1994
Ironbridge to Canning Town improvements 53 1994 1997
Prince Regent lane(Al 12) junction 36 1994 1996
East Ham Manor way(A117) junction 33 1994 1996

All schemes are subject to the availability of funds and the satisfactory completion of statutory procedures.