HC Deb 07 July 1992 vol 211 c137W
Mrs. Helen Jackson

To ask the President of the Board of Trade when he expects to receive the published report from the nuclear installations inspectorate on the long-term safety reviews for Dungeness A, Oldbury, Sizewell A, Trawsfynydd and Wylfa.

Mr. Eggar

The Health and Safety Executive has already published the nuclear installations inspectorate's detailed findings on Berkeley, Bradwell, Calder Hall, Chapelcross, Hinkley Point A, and Hunterston A. I understand that Nuclear Electric's safety reviews for the remaining Magnox power stations are currently at various stages of assessment by the NII. However, the need for thoroughness in the assessment of these reviews precludes the setting of a precise timetable. Nevertheless, I am assured by the NII that its findings on each of the remaining stations will be published at the earliest opportunity with the last of them, which will address Wylfa, being completed in 1994.