§ Mr. Gareth WardellTo ask the Secretary of State for Wales if he will publish full details of the timetable for the completion of the missing sections of the M4 between Baglan and Lon-las, including the dates of awarding of contracts.
§ Sir Wyn Roberts; Work is under way on the Earlswood-Lon-las section, which is due for completion in spring 1993. Work is planned to start on the Briton Ferry-Earlswood section of the M4 in 1991–92. Construction of the Baglan-Briton Ferry section is planned to start six months later, so that both sections are completed together by 1995. It is too soon to say when contracts will be awarded.