§ Mr. WigleyTo ask the Secretary of State for Wales if he will list in theOfficial Report all those road improvement schemes whose cost is estimated to be in excess of £1 million, on the A470 north-south trunk road in Wales, which are currently either committed, at planning stage or in the preparation pool, indicating for each scheme (a) the approximate length of roadway involved, (b) the standard of road after improvement, and (c) the approximate date or latest information when it is hoped the work will commence.
§ Sir Wyn RobertsThe following schemes are under construction, all to single carriageway standard:
Length (Miles) Llanidloes bypass 2.5 Brecon bypass—Felinfach 1.4 Junction Improvements South of Llangurig 0.8 Details of schemes in the forward programme are shown in "Roads in Wales: Progress and Plans for the 1990s".