HC Deb 13 February 1990 vol 167 c168W
Mr. David Shaw

To ask the Secretary of State for Transport which year's budget contained the relevant expenditure, in relation to the relevant authorities, in respect of the following works on the M2/A2:(a) London boundary to M2 provision of lighting and provision of hard shoulders, (b) Brenley to Harbledown provision of lighting and provision of central reserve safety fencing, (c) Harbledown to Bridge provision of central reserve safety fencing, (d) Shepherdswell provision of lighting and (e) Jubilee Way to Dover alterations to road markings and removal of lay-bys.

Mr. Atkins

Expenditure was contained in the following years:—

A2

(a) London boundary to M2
Hardshoulders: 1985–86 to 1989–90 inclusive.
Lighting: Not yet allocated
(b) Brenley to Harbledown
Lighting: Not yet allocated.
Central reserve safety fence: Not yet allocated.
(c) Harbledown to Bridge
Central reserve safety fence: Not yet allocated.
(d) Shepherdswell
Lighting: 1989–90.
(e) Jubilee Way to Dover
Alterations to road markings: 1989–90
Removal of lay-bys: 1989–90.