HC Deb 06 February 1990 vol 166 c563W
Mr. Pawsey

To ask the Secretary of State for Transport when motorway lighting will be installed on the M1 from Watford Gap to its junction with the M6.

Mr. Atkins

Motorway lighting is at present being installed from Watford Gap (junction 17) to Crick (junction 18) and will be completed by the end of this month. Further extension from Crick to the M6 junction (junction 19) is planned and should go ahead during the 1990–91 financial year.