§ 13. Mr. McFallTo ask the Secretary of State for Energy what is the latest estimate available to him from the South of Scotland electricity board and the Central Electricity Generating Board of the cost of(a) doubling and (b) trebling the carrying capacity of the interconnector between Scotland and England.
§ 47. Mr. McAvoyTo ask the Secretary of State for Energy what meetings or representations he has recently had on the potential transmission of spare electricity generating capacity from Scotland into England and Wales.
§ Mr. Michael SpicerI understand that the industry announced today that it will, in the near future, proceed with preparatory work which will involve a full environmental study and discussions with local authorities and other interested bodies with a view to upgrading the interconnector to 1.6 GW by 1994. The cost of upgrading the interconnector and the decision to proceed beyond preparatory work will be a matter for commercial negotiation.