HC Deb 13 February 1989 vol 147 cc44-5W
Mr. Ingram

To ask the Secretary of State for Scotland if he will give the building costs estimated and actual for hospitals started since 1979.

Mr. Michael Forsyth

Details of all hospital developments are not held centrally as minor capital projects are delegated to health boards and the Department only keeps records of all projects over £1 million.

The relevant information is detailed below:

Projects started since 1979
£ million
Total tender cost Total cost1
Argyll and Clyde
Dunoon and District General Hospital 0.9 1.0
Ayrshire and Arran
Biggart Hospital 1.2 1.2
Borders
Hay Lodge, Peebles 2.3 2.4
Borders General, Huntlyburn 23.7 30.5
Dumfries and Galloway
Annan Hospital 1.1 1.l
Fife
Whytemans Brae, Kirkcaldy 3.6 5.6
West Fife District General Hospital 8.7 10.5
Forth Valley
Bonnybridge 3.3 3.3
Royal Scottish National Hospital 2.4 2.5
Sauchie Hospital 1.0 1.2
Falkirk Royal Infirmary 7.9 8.5
Stirling Royal Infirmary 11.4 18.1
Greater Glasgow
Stobhill Hospital, Glasgow 1.5 1.6
Gartloch Hospital, Glasgow 2.0 2.2
Leverndale Phase I 4.6 4.5
Lennox Castle 2.4 2.6
Highland
Raigmore Hospital, Inverness 17.2 31.0
Caithness Phase II 7.3 9.1
Lanarkshire
Kirklands Residential, Bothwell 1.1 1.0
Kirklands Phase I 1.9 2.4
Kirklands Phase I 1.8 2.3
Lothian
Astley Ainslie Hospital, Edinburgh 1.6 2.0
Hermanflat Hospital, Haddington 2.4 2.7
Royal Victoria Hospital, Edinburgh 5.9 7.0
Western General Phase II 7.4 7.7
Shetland
Montfield Hospital 2.3 2.6
Tayside
Murray Royal, Perth 0.9 12
Perth Royal Infirmary, geriatric assessment 0.9 1.4
Royal Liff, Dundee 1.0 1.0
1 The total column represents the most up-to-date information available. Building contracts lasting more than 2 years are subject to variation of price clauses; costs therefore increase in line with inflation in the building industry.