§ Mr. Greg KnightTo ask the Secretary of State for Energy what is the land use impact of electricity produced by nuclear power compared to that used by coal.
§ Mr. Michael SpicerThe CEGB advises me that the construction process of an 1,800 MW coal-fired power station equipped with FGD plant requires some 100 hectares of land of which about half would be retained for operational use. The construction process of a 1,200 MW PWR nuclear power station requires some 75 hectares of which about a third would be retained for operational use.
424WIn general a coal-fired power station requires more land for operational use than a nuclear power station.