HC Deb 18 December 1989 vol 164 cc101-2W
25. Mr. Alan W. Williams

To ask the Secretary of State for Energy what is his latest estimate of the cost of completion of Sizewell B and the average operating cost per kilowatt hour.

Mr. Michael Spicer

This is a matter for the CEGB. I will ask the chairman to write to the hon. Gentleman.

Mr. Stern

To ask the Secretary of State for Energy how frequently he intends to review the ongoing construction costs of Sizewell B.

Mr. Michael Spicer

The CEGB is providing my Department with six-monthly progress reports on Sizewell B, including construction costs. Nuclear Electric will continue this arrangement and has made clear that it is committed to completing the station to time and present cost estimates.