HC Deb 11 May 1988 vol 133 cc176-81W
Mr. Robin Cook

To ask the Secretary of State for Social Services if he will list by regional health authority and special health authority all capital schemes costing over £1 million which are currently in progress; and if he will give the estimated date of completion.

Mrs. Currie

The information requested is included in the table.

Schemes Under Construction Contract Dates Start Complete Estimated Completion
Hartlepool DGH Scheme 3 Phase 2 4 January 1988 4 April 1990 4 April 1990
Royal Victoria Infirmary Scheme 1 Phase 5 4 January 1988 4 July 1991 4 July 1991
South Cleveland GH Hemlington Brokerage (D) 8 February 1988 8 October 1989 8 October 1989
South Shields General Scheme 3 Phase 1 24 January 1987 25 January 1990 25 January 1990
St. Georges Hospital Boilerhouse 29 June 1987 29 December 1988 7 November 1988
Westmoreland DGH Scheme 1 Phase 1 7 September 1987 7 September 1990 7 September 1990
Yorkshire RHA
Castle Hill Hospital Surgical Development 23 November 1987 11 February 1990 11 February 1990
High Royds Hospital Upgrading of Six Wards 2 June 1986 2 November 1988 2 November 1988
Hull Royal Infirmary PGMEC 2 November 1987 30 April 1989 30 April 1989
Pontefract Day Surgical Unit 24 August 1987 17 February 1989 31 December 1988
Scarborough Geriatric Day Hospital and Wards 25 May 1987 26 November 1988 26 November 1988
Scunthorpe DGH Phase 3B A and E Block 15 September 1986 10 October 1988 10 October 1988
Scunthorpe DGH Phase 4A(2) Four Storey Block 20 July 1987 18 August 1989 18 August 1989
Seacroft Hospital Leeds EPD Wards 4 January 1988 2 January 1989 2 January 1989
Staincliffe DGH Pathology Department (Extns and Imps) 9 March 1987 13 March 1989 13 March 1989
Staincliffe DGH Phase 1 (Nucleus) 7 January 1985 6 July 1988 3 August 1988
Trent RHA
Bassetlaw DGH Phase 2 30 June 1986 22 September 1989 6 October 1989
Doncaster Royal Infirmary Childrens Unit 20 October 1986 6 November 1988 6 November 1988
Doncaster Royal Infirmary Phase 2 Path. Lab. 17 August 1987 9 September 1989 9 September 1989
Glenfield DGH Phase 2 11 May 1987 7 April 1990 25 May 1990
Kendray-Sub Phase 2B-Mental Illness Unit/Esmi 2 November 1987 7 August 1989 7 August 1989
Kings Mill—Mortuary and Histopathology 13 April 1987 22 July 1988 22 August 1988
Leicester Royal Infirmary Phase 4B 26 October 1987 1 July 1990 1 July 1990
Louth County 28 September 1987 12 February 1989 12 February 1989
Montagu Mexborough Wards and Theatres 3 February 1986 9 May 1988 4 July 1988
Northern General Renal Unit 8 February 1988 21 July 1989 21 July 1989
Pilgrim Hospital (Boston) Support Services 6 April 1987 30 September 1988 12 October 1988
Sheffield Childrens Phase 1 Development 14 April 1986 6 May 1988 October 1988
East Anglian RHA
Kings Lynn London Road Contract 2 15 June 1987 2 October 1988 2 October 1988
Northgate—Conv. of Maternity Unit to Geriatric 8 June 1987 2 January 1989 2 September 1988
North West Thames RHA
Central Middlesex Psychiatric Unit 18 November 1985 16 November 1987 31 March 1988
Charing Cross G.U. Unit 2 November 1987 7 October 1988 7 October 1988
Clayponds Geriatric Unit (Nucleus) 1 February 1987 14 October 1988 14 October 1988
Colindale Psychogeriatric Hospital 9 November 1987 7 August 1989 7 August 1989
Edgware General Hospital 28 October 1985 1 July 1988 1 July 1938
Gossoms End Day Unit 23 February 1987 10 October 1988 10 October 1938
Hemel Hempstead Phase 2—Unit for the Elderly 1 February 1988 10 November 1989 10 November 1939
Lister Residential Accommodation 12 March 1984 10 June 1985 10 June 1985
Marjory Waren Medical Centre 2 November 1987 1 November 1988 1 November 1938
Mount Vernon Medical Block 18 May 1987 18 December 1987 24 February 1938
North London Blood Transfusion Centre—Enabling Weeks 1 June 1987 14 October 1988 14 October 1988
North London Blood Transfusion Centre 1 June 1987 14 October 1988 14 October 1988
OE 11 Reorganisation of Acute Facilities Phase 1 3 August 1987 26 November 1989 26 November 1989
St. Alban's Redevelopment of Main Phase 17 November 1986 23 January 1989 31 January 1989
St. Stephen's Aids Centre 27 April 1987 1 April 1988 1 April 1988
North East Thames RHA
Barking Elderly Care Services Department April 1987 December 1988 10 February 1989
Chingford M.I. Residential and Day Unit 4 January 1988 3 February 1989 3 February 1989
Clacton Community Hospital Phase 2 1 December 1986 28 February 1988 17 May 1988
East Ham Memorial Accommodation for Mentally Ill 4 January 1988 30 June 1989 30 June 1989
Harold Wood Phase 2 School of Nursing 6 May 1986 8 September 1987 29 April 1988
High Wood—Extension to Laurels 27 April 1987 8 July 1988 21 September 1988
London Hospital (Mile End) 2 February 1987 29 April 1989 1 May 1989
North Middlesex Geriatric and Catering 17 March 1986 16 March 1988 16 June 1988
Rochford Geriatric Wards June 1986 March 1988 27 June 1988
St. Ann's Geriatric Unit 3 August 1987 27 January 1989 31 March 1989
St. Ann's M.I. Day Hospital and ESMI 6 October 1986 30 November 1987 3 May 1988
Whipps Cross Phase 1 18 April 1988 19 November 1990 19 November 1990
Whittington Redevelopment Phase 1 2 November 1987 13 August 1990 13 August 1990
South East Thames RHA
Eastbourne New DGH Phase 2 23 June 1986 31 December 1988 31 December 1988
Faversham Hospital Geriatric Wards 2 March 1987 2 June 1988 2 June 1988
Hastings DGH Pre-phase Works 23 June 1986 22 December 1987 16 February 1988
Medway DGH Phase 38 6 October 1986 31 March 1989 14 June 1989
R.V.H. Folkestone Phase 2 2 March 1987 25 November 1988 25 November 1988
Regional Distribution Centre 17 December 1987 13 October 1988 13 October 1988

Schemes Under Construction Contract Dates Start Complete Estimated Completion
St. Thomas' Hospital—South Wing 1 June 1987 31 May 1989 31 May 1989
South West Thames RHA
Bognor Community Hospital 1 February 1988 30 July 1990 30 July 1990
Crawley Hospital Phase 4 13 October 1986 12 August 1988 April 1988
Earls Court Ambulance Station 28 September 1987 27 February 1989 27 February 1989
East Surrey DGH Phase 2 Frame Contract 23 November 1987 22 May 1990 22 May 1990
Horsham Hospital Mental Illness Unit 7 September 1987 7 June 1989 7 June 1989
Mid Sussex Phase 1 14 July 1986 13 July 1989 30 November 1989
Royal Surrey County Guildford Phase 2 1 September 1986 30 November 1989 30 November 1989
St. George's Phase 2 A and E Extension 9 November 1987 14 August 1988 14 August 1988
Wessex RHA
Bournemouth DGH—Phase 1 (Nucleus) 6 August 1984 6 May 1987 4 August 1988
Odstock Hospital Salisbury—Phase 1 (Nucleus) 4 January 1988 24 May 1991 24 May 1991
Poole General Hospital—ESNI Assessment Unit—Day Hospital 20 July 1987 19 July 1989 19 July 1989
Royal United Bath—Operating Theatres 28 November 1985 14 February 1989 7 March 1989
St. Ann's Canford Cliffs—Extension Contract 1 19 October 1987 10 July 1989 27 July 1989
St. Martin's Bath Geriatric Wards 27 May 1987 8 March 1989 8 March 1989
St. Mary's Portsmouth 24 August 1987 22 November 1989 22 November 1989
St. Mary's—Isle of Wight—Phase 38 (Nucleus) 28 October 1985 11 September 1988 14 May 1989
Westbury Replacement of Sambourne Hospital 4 January 1988 21 May 1989 21 May 1989
Oxford RHA
Buckingham—Phase 1 23 November 1987 25 October 1989 25 October 1989
Heatherwood Catering Pharmacy Workshops and Stores 7 December 1987 31 August 1989 31 August 1989
John RadclifTe Hospital—Phase 3 26 May 1987 25 November 1988 25 November 1988
Kettering—New Theatres and Spencer Ward 20 July 1987 9 January 1989 9 January 1989
Milton Keynes DGH—NI Unit 18 May 1987 14 April 1989 14 April 1989
Stoke Mandeville—OPD—Hospice 4 January 1988 3 July 1989 3 July 1989
Stoke Mandeville—Pathology 5 October 1987 3 February 1989 3 February 1989
Wexham Park—Rehabilitation Unit 19 November 1986 17 August 1988 17 August 1988
South Western RHA
Cheltenham General Phase 18 19 August 1985 16 May 1988 1 August 1988
Cirencester Memorial Replacement and ESNI Beds 6 January 1986 15 August 1988 30 April 1988
Frenchay DGH Phase 1 7 July 1986 3 March 1989 14 July 1989
Glenside Sub—regional Secure Unit 5 January 1987 5 July 1988 5 July 1988
Gloucester Royal Phase 4B 7 April 1986 13 January 1989 13 January 1989
South Molton Hospital Geriatric and GP Unit 24 February 1986 19 February 1988 6 April 1988
Southmead Hospital—Pathology Phase 1 16 March 1987 27 March 1989 27 March 1989
Torbay DGH Geriatric Wards 1 February 1988 18 August 1989 18 August 1989
Williton New Geriatric Hospital 24 November 1986 26 August 1988 26 August 1988
West Midlands RHA
Bromyard Community Hospital 16 June 1986 4 September 1988 13 May 1988
Burton (Outwoods) Psychiatric/Temporary Maternity 22 September 1986 19 March 1988 2 June 1988
Burton on Trent DGH (Central Production Unit) 13 October 1986 27 May 1988 27 May 1988
City General Stoke Surgical Accomm. (Nucleus) 11 March 1985 2 September 1988 4 September 1988
Dudley—Guest Rehabilitation Unit 6 April 1987 6 October 1988 6 October 1988
Edward Street—Psychiatric/Geriatric 1 September 1986 28 November 1988 8 December 1988
Good Hope Phase 2 6 January 1986 1 February 1988 31 May 1988
Good Hope Phase 3A 7 July 1986 3 January 1988 30 April 1988
Queen Elizabeth Birmingham—Phase 3 Contract 1 7 April 1986 31 July 1988 1 September 1988
Telford DGH Phase 1 (Nucleus) 26 November 1984 26 May 1988 31 June 1988
Walsall Phase 4A and 4B (Nucleus) 7 January 1985 7 July 1988 2 October 1988
Mersey RHA
Alder Hey Paed. Cardiology and Inst. of Child Health 18 March 1985 18 September 1987 April 1988
Broadgreen Development Phase 1 (Nucleus) 6 January 1986 4 January 1988 31 May 1988
Clatterbridge Medical Unit (Nucleus) October 1986 September 1988 4 October 1988
Fazakerley Hospital Acute M.I. Unit 11 May 1987 3 June 1988 8 July 1988
St. Helens Redevelopment Phase 1 Boiler House 7 April 1986 3 January 1988 30 July 1988
Warrington DGH Phase B (Nucleus) 17 March 1986 30 April 1988 30 April 1988
North Western RHA
Chorley DGH Geriatric Unit 29 June 1987 25 December 1988 24 January 1989
Fairfield Phase 1 5 July 1985 1 February 1988 15 April 1988
Manchester Royal Infirmary Catering Block 1 September 1987 27 November 1989 22 May 1989
Manchester Royal Infirmary Phase 2 14 July 1986 13 January 1990 5 January 1990
Manchester Royal Infirmary Service Complex 1 September 1986 23 September 1988 23 September 1988
Oldham DGH Phase 1 11 February 1985 7 February 1988 16 March 1988
Queens Park Blackburn Phase 1 Paediatric 4 June 1984 4 June 1986 18 March 1987
Royal Preston Pathology Phase 2 28 September 1987 28 November 1989 28 November 1989
Whelley Hospital Phase 1 26 May 1987 24 November 1989 24 November 1989

Schemes Under Construction Contract Dates Start Complete Estimated Completion
Non RHA
Blood Products Manufacturing Unit Elstree 1 May 1983 1 November 1985 30 April 1988
Great Ormond Street Boiler Plant Replacement 18 August 1986 30 June 1988 30 June 1988
Hammersmith Hospital Redevelopment Phase 1 September 1985 May 1988 31 March 1988
Maudsley Hospital Redevelopment Phase 1A 1 June 1987 23 October 1988 21 November 1988
Moorsfields Eye Hospital—Redevelopment Phase 2B 5 February 1988
National Heart and Chest Centre Brompton Phase I 2 March 1987 23 July 1989 23 July 1989

Total number of schemes = 134