§ Mr. John BrowneTo ask the Secretary of State for Wales what is the design traffic flow for the improvement on the A55 at Conwy; and what are the total estimated costs.
§ Mr. Wyn RobertsThe design traffic flows through Conwy tunnel based on the 1981 forecast for the 16-hour two-way August peak flows in the design year 2003 were:
- High growth 36,590 vehicles/day
- Low growth 29,730 vehicles/day
The total estimated cost for the improvement of the A55 at Conwy is £160 million.