HC Deb 13 February 1987 vol 110 c378W
Mr. Roy Hughes

asked the Secretary of State for Transport if he will make a statement regarding the progress of repair work on the Severn bridge.

Mr. Peter Bottomley

Work for the strengthening of the Severn crossing is well under way. The first two contracts, for the provision of improved access and for strengthening the Aust viaduct at the eastern end of the crossing, are complete. A third contract for the supply of new hangers for the suspension bridge is in progress. Tenders for the fourth contract for the major strengthening works are due back on 23 February 1987; this is planned to be a two-year contract, to be completed in spring 1989. A fifth contract, for protection works to some of the river piers against possible shipping collision, is expected to be let later this year. Following the major strengthening work, the entire crossing will be completely resurfaced in 1989–90, for the first time since it was opened in 1966.