HC Deb 27 February 1984 vol 55 cc56-7W
Sir Raymond Gower

asked the Secretary of State for Wales if he will give details of progress with new hospital projects and extensions in the Principality.

New hospital projects and extensions in the course of construction, or due to start in 1984
District Scheme Start date Expected completion Total cost (£000's)
Clwyd Wrexham DGH Scheme 1 7 September 1981 January 1985 13,211
East Dyfed St. David's, Carmarthen 21 September 1981 September 1984 2,270
Bryntirion Phase II 6 September 1982 September 1985 2,658
Llanelli General Hospital June 1984 November 1987 19,773
Gwynedd Ysbyty Gwynedd 29 March 1976 June 1984 33,543
Llandudno Phase I May 1984 May 1987 1,597
Mid Glamorgan Bridgend DGH 30 June 1980 January 1985 22,450
St. Tydfil's Adaptations 2 March 1984 September 1985 3,302
Powys Ystradgynlais Community Hospital April 1984 May 1986 3,222
South Glamorgan Llandough Obstetric and Associated Works 15 February 1984 1987–88 7,719
Prince of Wales Renovations—all schemes 2,331
Gas Supply March 1984 June 1984 136
Distribution of Gas June 1984 July 1984 50
Boilerhouse April 1984 September 1984 350
Electricity Mains May 1984 September 1984 150
Upgrading of Wards Phase 1 September 1984 June 1985 650
Upgrading of Wards Phase 2 July 1985 April 1986 150
Upgrading of Nurses Accommodation November 1984 June 1985 145
Provision of Modular Operating Theatres September 1985 June 1986 700
West Glamorgan Morriston Nucleus and Upgrading 1 December 1980 March 1985 16,672
Morriston Geriatric Scheme June 1984 March 1986 2,700
Neath OPD 17 November 1982 July 1984 2,090
Singleton Pathology/Mortuary May 1984 May 1986 3,000

Forward to